Residents:
The Township has contracted with AMS (Asphalt Maintenance Solutions) to complete Cape Seal work in select neighborhoods.
Unsure what Cape Seal is? Please find an informational video HERE.
Below is the tentative schedule for Road Work, but it is subject to change with forecasted rain events:
UPDATED SCHEDULE AS OF (6/18)
June 19th (Thurs) - Chip Seal
- Kristines Way
- Deer Run
- White Horse
- Coachlight Cir
- Carriage House Ln / Apple Ln
June 20th (Fri) Chip Seal
- Hammersmyth Ct
- Bennington Ct
- White Pine Way
- Branch Rd
- Ellen Way
- Harvest Glenn Dr
- Hagey Rd
- Devon Circle
- Walker Circle
- Caln Circle
Week of July 2nd
- Sweeping and Installing the Type II Slurry Seal
Please feel free to contact The Township with any questions at 215-256-8087